Professional Generator Set Manufacturer

Power That Never Stops When Darkness Falls, NovArk Powers Through
Our company was established in 2013 and consists of four branches nationwide. As one of the leading OEM manufacturers of diesel generators in China, we have earned a strong reputation and multiple awards over the years, meeting diverse requests from markets around the world.
Home / All / NovArk Power supply guarantee solution for large construction enterprises / Yingkou Xinjing Ironworks — Diesel Generator Project

Yingkou Xinjing Ironworks — Diesel Generator Project

Update Time:2026/9/1 13:33:38
Yingkou Xinjing Ironworks — Diesel Generator Project
Yingkou Xinjing Ironworks — Diesel Generator Project
Case Study: Yingkou Xinjing Ironworks — Diesel Generator Project
From "Blast Furnace Crisis on Blackout" to "Zero-Interruption Smelting Assurance" — A Full-Process Industrial Power-Resilience Engagement
01 Project Background: The Situation Before We Engaged

Yingkou Xinjing Ironworks (hereinafter referred to as "Xinjing") operates a 1,800 m³ blast furnace complex on the southern coast of the Liaodong Peninsula, with an annual hot-metal output exceeding 2 million tons. Its production chain — covering sintering, pelletizing, blast furnace ironmaking, and BPRT waste-heat recovery — is entirely dependent on continuous grid power.

Before our involvement, the plant's emergency power infrastructure exhibited the classic "high-risk, low-readiness" pattern typical of legacy ironworks:

  • Aging single-point generators: The two existing 350 kW standby units were over 12 years old, with output attenuated by ~25 %. During a 2024 cold snap, both units failed to start simultaneously, forcing an emergency furnace blowdown.
  • No N+1 redundancy: Critical security loads — cooling-water pumps, hydraulic stations, dust-removal systems, and gas-cutoff valves — were all fed from a single generator. Any unit failure meant immediate risk of tuyere slag-back or gas-line depressurization.
  • Slow manual switching: ATS panels were outdated; mean switchover time after grid loss exceeded 45 seconds, far beyond the 10-second window needed to prevent tuyere damage.
  • No remote monitoring: Generators had no telemetry. During a midnight outage, the on-duty engineer had to physically run to the engine room to check oil pressure and battery voltage.
  • Regulatory pressure: Liaoning's 2024 ultra-low-emission inspection required CEMS (continuous emission monitoring) to run uninterrupted. Power loss meant data gaps and potential fines of up to ¥500,000 per violation.
Worst-case incident pre-engagement: In January 2025, a 90-minute grid outage during a winter storm caused the No.2 blast furnace cooling system to lose pressure. Three tuyere assemblies suffered slag-back; the furnace required 36 hours of forced maintenance at an estimated direct loss of ¥3.8 million.
02 Tender Purpose & Bidding Process
2.1 Tender Objectives

Xinjing launched a public tender for a comprehensive diesel-generator upgrade with the core goals of "blast-furnace-grade reliability, sub-10-second switchover, ultra-low-emission compliance, and full lifecycle traceability":

  • ✓N+1 redundancy: Minimum two independent generator sets per critical load zone, capable of automatic load-sharing.
  • ✓Sub-10-second ATS switchover: Guaranteed transition from grid to generator power within 10 s of outage detection.
  • ✓72-hour continuous runtime: On-site fuel storage sufficient for three days of full-load operation.
  • ✓CEMS-compliant power: Dedicated UPS + generator circuit for all emission-monitoring equipment.
  • ✓Smart O&M platform: IoT-based remote monitoring integrated with the plant's existing MES dashboard.
2.2 Bidding Process
  • Pre-qualification: Only manufacturers or authorized OEM dealers with ISO 9001/14001 certification and at least 3 iron & steel industry references were admitted.
  • On-site load audit: Shortlisted bidders were required to map all security loads per electrical room (blast furnace, hot stoves, dedusting, BPRT, pelletizing) and submit a tiered capacity plan.
  • Technical bid scoring: Weighted heavily on switchover time (≤10 s), noise & emission compliance (GB 20891-2024), anti-corrosion design for coastal salt-spray environment, and IoT protocol compatibility with Siemens PCS7.
  • Live demonstration: Finalists were invited to the plant to perform a black-start drill on a test bench; we achieved full load acceptance in 7.5 seconds.
  • Award: We were selected as the primary supplier under a "framework + phased delivery" contract covering 6 generator sets and a central monitoring platform.
03 Post-Award Objectives

The client's intent was not merely to replace aging machines but to build a "plant-wide power resilience backbone":

  • ✓Every critical subsystem (furnace cooling, dedusting, gas safety, CEMS) must have dedicated, independently-switched backup power.
  • ✓All switchovers must be fully automatic — zero human intervention required during the 0–10 s window.
  • ✓The plant control room must see real-time generator health (oil pressure, coolant temp, battery SOC, run hours) for every unit on a single screen.
  • ✓Compliance evidence (test reports, run logs) must be exportable for environmental-authority audits at one click.
04 Why They Found Us (Differentiation & Trust Factors)
1. Proven steel-industry track record: We had previously delivered 800 kW + 630 kW generator sets to a sister sintering plant in Anshan, with two years of zero unplanned downtime.
2. Deep understanding of blast-furnace loads: We correctly identified that the hydraulic pump inrush current (≈3.2× rated) was the hidden killer of previous generator starts — a detail none of the other four bidders had mentioned.
3. Coastal anti-corrosion expertise: Yingkou's salt-spray environment demands C5-M grade protection. Our proposed epoxy-zinc-rich coating + stainless-steel fasteners exceeded the tender's C4 requirement.
4. Live drill performance: During the on-site black-start test, our 630 kW unit reached 400V/50Hz and accepted full load in 7.5 s — the only bidder to beat the 10 s threshold.
5. Siemens PCS7 integration: Our IoT gateway natively spoke Profinet, meaning zero middleware — the plant's existing SCADA could read generator tags without any custom programming.
05 Our Proposed Solutions & Recommendations

We did not sell "diesel generators" — we sold "uninterrupted ironmaking capability."

Dimension Solution Proposed to Xinjing Pain Point Addressed
Capacity Tiers Blast furnace security load (415 kW) → 630 kW standby; BPRT hydraulic station (350 kW) → 500 kW; dedusting fans → 800 kW; CEMS → dedicated 30 kW UPS-fed circuit. Every critical subsystem independently protected; no single point of failure.
N+1 Parallel Architecture Two 630 kW units in parallel for the furnace zone; automatic load-sharing with PLC-based load-shedding if one unit trips. Single-unit failure no longer endangers the furnace; seamless takeover.
Ultra-Fast ATS Dual-PLC controlled ATS cabinets with 8-second design target; inrush-preheating circuit for hydraulic pumps to absorb 3.2× starting current. Switchover well within the 10 s safety window; no tuyere damage risk.
Coastal Anti-Corrosion C5-M rated epoxy-zinc-rich coating, stainless-steel fasteners, IP55 control cabinets with positive-pressure ventilation, tropical-grade radiator. Engineered for 25-year life in Yingkou's salt-spray coastal climate.
Smart Monitoring IoT edge gateway (Profinet native) pushing oil pressure, coolant temp, battery SOC, run hours, and fuel level to the central SCADA; automatic SMS/WeChat alerts on alarm thresholds. Control-room operators see every generator on one screen; midnight surprises eliminated.
Fuel & Emissions On-site 10,000 L underground diesel tank (72 h @ full load); DOC+DPF exhaust after-treatment; noise enclosure ≤75 dB @ 7 m. Meets Liaoning ultra-low-emission standards; no CEMS data gaps during outages.
06 Implementation & Execution

After the framework award, we executed a six-phase rollout synchronized with the plant's scheduled maintenance windows to ensure zero production loss:

  • Phase 1 — Load mapping & factory acceptance: Within 10 days we audited all six electrical rooms, confirmed actual security loads vs. nameplate ratings, and performed FAT (factory acceptance test) on each generator set at our works — including a 2-hour full-load run and a hot-soak restart test.
  • Phase 2 — Civil & foundations: Poured vibration-isolated concrete plinths (200 mm thick, rebar-reinforced) inside the blast-furnace and dedusting electrical rooms; installed spring-damper mounts to protect sensitive adjacent instrumentation.
  • Phase 3 — Delivery & rigging: Used the plant's 80-ton overhead crane during a 36-hour furnace maintenance window to position the 630 kW parallel sets; completed all cable pulls (3×185 mm² + 1×120 mm²) within 28 hours.
  • Phase 4 — ATS integration & Profinet commissioning: Wired dual-PLC ATS cabinets, integrated generator tags into the existing Siemens PCS7 SCADA; validated data polling at 500 ms intervals.
  • Phase 5 — Black-start drills: Conducted three live grid-loss simulations per zone. Best result: 7.3 s from grid-loss detection to 100 % load acceptance on the furnace cooling circuit.
  • Phase 6 — Training & handbook: Delivered a 40-page Blast Furnace Backup Power SOP in Chinese, trained 18 electricians and 6 control-room operators across two 8-hour sessions, and established a quarterly inspection cadence.
07 Final Results (Quantified Value)

After 14 months of continuous operation, the project delivered measurable outcomes:

Mean Switchover
7.4 s
From grid-loss detection to 100% load acceptance.
Unplanned Downtime
0 hrs
Zero security-load interruptions since go-live.
CEMS Compliance
100%
Zero data gaps during two grid outages.
Cost Avoidance
¥4.2 M
Estimated loss prevented in the first year alone.
  • ✓Zero security-load interruptions: Since commissioning, the plant has weathered two grid disturbances (one 4-hour, one 11-hour). All furnace cooling, hydraulic, and dedusting loads transferred automatically — not a single tuyere was lost.
  • ✓Sub-8-second resilience: The average switchover time of 7.4 s is well inside the 10 s safety envelope, effectively eliminating the risk of slag-back during future outages.
  • ✓Regulatory zero-defect: During the 2026 Liaoning ecological-inspection campaign, Xinjing's CEMS logs showed 100 % uptime — the only plant in the Bayuquan cluster to achieve this.
  • ✓Operational peace of mind: The control-room SCADA now displays all six generator sets on one screen; the plant manager reports "sleeping through thunderstorms for the first time in a decade."
  • ✓Expanded partnership: On the strength of this engagement, Xinjing awarded us the 2026 maintenance contract for all generator sets and added a 500 kW unit for the new pelletizing line.
08 Client Testimonial
"Before this upgrade, every storm front meant a trip to the engine room and a prayer that the old gensets would start. Now the SCADA pings once and the furnace is protected — automatically, every time. For a blast furnace, that reliability isn't a convenience; it's the difference between a normal shift and a four-million-yuan disaster. This team understood our business, not just our electrical drawings." — Chief Engineer, Yingkou Xinjing Ironworks Power Department
Confidential · For internal reference and client presentation only · © 2026 · Yingkou Xinjing Ironworks Diesel Generator Project

For checking suitable generator product for your project— Contact NovArk Power

Get a free power system design consultation for your diesel generator set project. Our engineers will analyze your requirements and deliver a tailored generator solution.