Hunan Xinwufeng Group Pig Farm Diesel Generator Project

— From "Power Outage = Mass Mortality" to "Unattended Zero-Downtime" Pig-Supply Assurance Practice
Hunan Xinwufeng Co., Ltd. is a state-owned listed swine enterprise under Hunan province, with a breeding sow capacity exceeding 270,000 heads and annual output surpassing 3 million heads. It operates numerous modern, intelligent pig farms — including Yongzhou Chuwang, Hengyang Aggregation Zone, Wangcheng Quanxin, and Xinhua Building-Style Pig Farm — where environmental control, feed lines, drinking water, deodorization, and wastewater treatment all rely entirely on grid power.
Before we engaged, Xinwufeng's backup power across farming bases exhibited the classic "scattered, chaotic, risky" pattern:
- Fragmented equipment sources: Each farm procured generators from local small vendors independently. Brands were mixed, power ratings were inflated, and units couldn't handle simultaneous startup of fans and water pumps.
- Manual switching: Most sites only had manually-started units. During nighttime outages nobody entered the site, causing heat stress or cold shock.
- High corrosion failure rate: In high-humidity, high-ammonia environments, standard control cabinets rusted and tripped within 6–8 months.
- Environmental & biosecurity pressure: Open-frame units produced black smoke and loud noise, triggering complaints and biosecurity threats.
- No pre-procurement standards: Supplier quality varied wildly and there was no unified acceptance checklist.
- ✓Transform "each-farm-buys-its-own" into a corporate-level centralized procurement model.
- ✓Complete delivery + installation + commissioning within 20 days of order placement.
- ✓Rigorously evaluate manufacturer authorization, farm project references, and after-sales systems.
- ✓Address farm-specific requirements: corrosion resistance, silent operation, and ATS auto-start.
- Public tender managed by Hunan Zhonglongrui; pre-qualification eliminated unqualified traders.
- Technical bids scored on tiered configuration, ATS + cloud monitoring, and 20-day delivery commitment.
- Commercial bids evaluated within a control price of RMB 2.886 million.
- We secured the leading comprehensive score and were awarded a designated-supplier slot.
The client's goal was not simply "buying a few machines" but establishing a "standardized backup-power foundation for all pig farms province-wide":
- ✓Automatic adoption of standard models for any new farm.
- ✓Unified acceptance checklist for legacy farm retrofits.
- ✓Real-time visibility of unit status and fuel consumption during outages.
We did not sell "equipment" — we sold "uninterrupted-power capability."
| Dimension | Solution Proposed to Xinwufeng | Pain Point Addressed |
|---|---|---|
| Model Standardization | Tiered by farm type: 100–200 kW / 300 kW / 400–500 kW; all Yuchai Tier-3 + 20% power margin. | Eliminated inflated ratings; fans and pumps start without tripping. |
| Farm-Specific Modification | IP54 sealed cabinets + epoxy anti-corrosion + exhaust extended 15m outside. | Resists ammonia corrosion and protects biosecurity. |
| Auto-Start & Monitoring | ATS (3–8s auto-start) + IoT module + cloud dashboard. | Unattended nighttime operation with zero mortality. |
| Silent & Eco-Friendly | Silent canopy ≤75dB + DPX after-treatment + oil-water separation. | Passes environmental assessments with no black smoke. |
| Delivery Standard | Factory-supplied "Farm Acceptance Package": load-test + ATS video + SOP. | Eliminates on-site acceptance disputes. |
| O&M Mechanism | Quarterly inspections + 4-hour response + annual load-run drills. | Shifts from "repair after failure" to proactive maintenance. |
- Inventory & risk mapping: Audited 23 on-site sets; produced risk rating tables prioritizing key farms.
- Pilot benchmark farm: Delivered 2×300 kW units at Yongzhou Chuwang with witnessed 0–8s switchover.
- Phased batch delivery: Closed-loop process (arrival → lift → ATS tuning → 30-min load → sign-off) within 20 days.
- Personnel empowerment: Trained farm electricians on the "Seven-Step Inspection Method" and cloud dashboards.
- Redeployment & retirement: Retired units bought back and redeployed to non-livestock construction sites.
- Monthly reporting: Submitted generation hours, auto-start counts, and fuel analysis to headquarters.
- ✓Supply assurance: Zero mortality incidents during cooperation; longest autonomous run was 11 hours.
- ✓Failure rate: Unplanned downtime dropped from ~15% to below 2%.
- ✓Compliance: Zero generator-related complaints filed post-installation.
- ✓Efficiency: Real-time monitoring of 40+ units; digital settlement and redeployment.
- ✓Continued partnership: Designated as "Preferred Supplier" for subsequent farm expansions.
"In the past, every thunderstorm kept me awake — I was terrified the night patrol would miss a power outage. Now my phone pings 'Chuwang #2 Unit Auto-Started — 78% Load' and I can sleep soundly. This is the level of power assurance a state-owned pig farm deserves." — Farm Manager, Yongzhou Chuwwang Sow Farm
Contact NovArk Power
Get a free power system design consultation for your diesel generator set project. Our engineers will analyze your requirements and deliver a tailored generator solution.
- Solution for Power Guarantee in Communication System
- NovArk Power Diesel Generator Set Financial System Power Guarantee Solution
- NovArk Power supply guarantee solution for large construction enterprises
- NovArk Power Medical System Power Security Solution
- NovArk Power Security Solution for Computing Power Center
- NovArk Power supply guarantee solution for large construction